Cross Road Paving Project Starting

6

The Cross Road Paving Project is a  $2.7M project funded by the State of Connecticut, not Waterford  residents, and is scheduled to start this week!  Please note, the  schedule below is just for reference and is subject to weather.  If you  have any questions, please contact the Public Works Office  at 860-444-5864 between the hours of 8am-4pm Monday through Friday.  The  Waterford Police Department will be updating residents on traffic,  detours, night work schedule and other daily updates as needed,  utilizing social media.  

RT 85 (Hartford Turnpike) to Foster Road

•     June 1-7, Utility Adjustments (manhole, water gates, gas valves)

•     June 8, mill 3.5 inches of asphalt off the road

•     June 9, install temp traffic markings for one lane in each direction

•     June 13-14, pave the first course

•     June 14, install temp traffic markings for one lane in each direction

Parkway South (I 06 South) to Foster Road

•     June 1-7, Utility adjustments (manhole, water gates, gas valves)

•     June 15, mill 3.5 inches of asphalt off the road

•     June 16, install temp traffic markings for one lane in each direction

•     June 20-21, pave the first course

•     June 21, install temp traffic markings for one lane in each direction

Entire Length of Road

•     June 22-24, pave the final course

•     June 28-29, line striping and July 1st, anticipated completion date

Thank you in advance for your cooperation during this paving project.

~Rob Brule, First Selectman Town of Waterford

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS